Expansion Continues at Valero
Valero Diamond Green Diesel 3 OSBL Piling Package
Baker’s Deep Foundations team has been engaged by Valero to perform an extensive test pile program on both timber and pre-cast concrete piles throughout various locations of its Port Arthur, Texas, refinery.
The test pile program includes static load tests along with dynamic testing on piling. When the test pile program is complete, the Deep Foundations team will commence production piling to support numerous tank and pipe rack foundations throughout the project site.
The magnitude of this project includes over 10,000 pre-cast concrete and timber piles. BGCI is excited to partner with Burns & McDonnell in support of the Valero Diamond Green Diesel 3 project and Valero’s ongoing expansion.